Construction Update

Construction Update is published periodically and provides information about the progress of major building and renovation projects. Information is provided to the Record by facilities management.

Medical Campus

BJC Institute of Health at Washington University

The building is nearly complete. The school will receive a Certificate of Occupancy Dec. 23. New building occupants will move in mid-January.

Renard, 4488 Forest Park, Supply Room, West and Mallinckrodt Institute of Radiology buildings

The lighting conservation project will replace all T12-lamped fixtures and magnetic ballasts with new energy-efficient T8 lamps and electronic ballasts in each of the buildings. In addition, automatic lighting controls will be installed to shut off lights when they are not needed.

Public lighting

Phase I of the Public Realm Lighting project is nearly complete. This phase included the installation of light fixtures on one side of each street within the Washington University Medical Center.

Danforth Campus

Brauer Hall

The project remains ahead of schedule. The exterior masonry is 70 percent complete. Permanent power is connected. The in-wall rough-in inspections are complete, and drywall is being hung in the lower and third-floor levels.

Brauer Hall chiller plant

The structural concrete and the structural steel are complete.

South 40 College Hall

The fireplace masonry is complete and ahead of schedule. Steel erection has begun.

The Corner Building

The retail restrooms are complete. The extra finishes for retail walls and ceilings have begun and will be finished in November.