Central Underground Parking Garage
Mass excavation and the retention system are both 90 percent complete. The ramp retaining wall is complete, and the perimeter foundation walls are 25 percent complete. Project completion is scheduled for Aug. 3, 2007.
Sam Fox School
The Sam Fox School of Design & Visual Arts was dedicated Oct. 25.
Snow Way Parking Garage
Expansion Phase II: Shotcrete walls and footings are complete. Interior footings are complete, as is level 2. Level 3 east was poured Oct. 26. Project completion is scheduled for Dec. 22.
Social Sciences/School of Law
The mass excavation is 95 percent complete. Footings have been placed along the western walls. Foundation walls soon will be placed at the southwest corner. The tower crane base has been set, and temporary power is being installed. Sub-floor sewers also are being installed.
University Center
The University has received 100 percent Design Development documents, and review comments have been returned to the design team. Design firm Tsoi/Kobus & Associates Inc. was to present the interior design at a Nov. 6 meeting. Construction is scheduled to begin in April 2007.