Danforth Campus construction update

Central Underground Parking Garage

Mass excavation and the retention system are both 90 percent complete. The ramp retaining wall is complete, and the perimeter foundation walls are 25 percent complete. Project completion is scheduled for Aug. 3, 2007.

Sam Fox School

The Sam Fox School of Design & Visual Arts was dedicated Oct. 25.

Snow Way Parking Garage

Expansion Phase II: Shotcrete walls and footings are complete. Interior footings are complete, as is level 2. Level 3 east was poured Oct. 26. Project completion is scheduled for Dec. 22.

Social Sciences/School of Law

The mass excavation is 95 percent complete. Footings have been placed along the western walls. Foundation walls soon will be placed at the southwest corner. The tower crane base has been set, and temporary power is being installed. Sub-floor sewers also are being installed.

University Center

The University has received 100 percent Design Development documents, and review comments have been returned to the design team. Design firm Tsoi/Kobus & Associates Inc. was to present the interior design at a Nov. 6 meeting. Construction is scheduled to begin in April 2007.