Construction Update for Danforth Campus

Construction Update is published periodically and provides information about the progress of major building and renovation projects. Information is provided to the Record by facilities management.

Sam Fox Arts Center

The dedication of the Sam Fox School of Design and Visual Arts is scheduled for Oct. 25.

Social Sciences/School of Law

The excavation is about 50 percent complete. Rock has been encountered in the western portion of the building footprint. Work began on the footings the week of Sept. 25.

University Center

The University has received 100 percent of the design development documents and review comments have been returned to the design team. Tsoi/Kobus & Associates will present the interior design at a meeting scheduled for Oct. 12.

Central Underground Parking Garage

Mass excavation is 80 percent complete. The retention system is 80 percent complete. The ramp retaining wall is 65 percent complete and the perimeter foundation walls are 5 percent complete. The project is on schedule.

Snow Way Parking Garage Expansion Phase II

The shotcrete walls are complete, the north footings are complete. The chiller plant walls are complete. The western two-thirds of the interior footings were 60 percent complete Sept. 1.