Social Sciences/School of Law Building
Work on the foundation is moving along the north wall from the west to the east. Footings for the east wall are in progress. Work is under way for the mechanical, electrical and plumbing installation beneath the central and northern floor slabs. Construction should be completed by June 2008.
University Center
The University has received 100 percent of the construction documents for the architectural design. The remainder of the design documents will be completed this month. Phase 1 subcontractor bidding is to begin immediately upon completion of all construction documents. Construction is scheduled to begin in April and will be completed by July 2008.
Central Underground Parking Garage
Mass excavation is 100 percent complete. The retention system is 100 percent complete. The ramp retaining wall is 100 percent and the perimeter foundation walls are 90 percent complete. The third elevated slab has been poured. The project is on a recovery schedule to expedite the construction of the garage, which will ensure that the University Center construction will begin in April. Project completion is scheduled for August 3.